Postby forestef on Thu Oct 17, 2013 2:10 pm

I am trying to close a change request, in the same manner as closing a work order, but cannot find a way to do so. Does anyone have any hints they can give me?

Thanks

Frank
forestef
Newbie
 
Posts: 1
Joined: Thu Oct 17, 2013 1:48 pm

Re: Closing Change Requests

Postby Oppie on Thu Oct 24, 2013 11:51 am

We have Alloy configured so that only certain job profiles can close Change Requests. This is because there are follow up actions to complete which are best assessed independently from the person who actualy did the change - by the Change Manager/Technical Authority.
e.g.
Was the change successful?
Did it have the desired benefts/outcomes.
Did it have a longer outage than stated in the implementation plan?
Did it fail?
etc.
Oppie
Junior
 
Posts: 2
Joined: Wed Oct 23, 2013 3:52 am

Re: Closing Change Requests

Postby eliaslynch on Mon Nov 18, 2013 11:39 am

forestef wrote:I am trying to close a change request, in the same manner as closing a work order, but cannot find a way to do so. Does anyone have any hints they can give me?


In v6 you must first complete a change request before you can close it. Is it marked completed?

You can change that of course, but that's by default.
--------
Elias
User avatar
eliaslynch
Senior
 
Posts: 212
Joined: Wed Jul 09, 2008 7:03 pm


Return to Alloy Navigator 6 Discussion

Who is online

Users browsing this forum: No registered users and 2 guests